Nigeria's power plants can, on paper, produce about 13,600 megawatts (MW). On most days, only about 4,000 to 5,000 MW reaches us (THISDAY). For more than 240 million people, that is like feeding a whole street from one pot of soup. Here is why, in the simplest terms possible.
This is the third piece in my plain-terms series. If you're new here, start with Fuel Subsidy in Plain Terms: Why It Had to Go and The Naira Was Never Strong: FX Unification in Plain Terms.
How electricity gets to your house
Think of water supply in an estate. Someone pumps the water, big pipes carry it across town, and small pipes bring it to each house. Electricity works the same way:
- Generation (the pump): power plants, mostly gas-fired, produce the electricity.
- Transmission (the big pipes): the government-owned Transmission Company of Nigeria (TCN) carries it across the country on high-voltage lines.
- Distribution (the small pipes): eleven Distribution Companies (DisCos), such as Ikeja and Kano, bring it to your street, bill you and collect the money.
The key point: power flows forward, but money flows backward. You pay the DisCo, the DisCo pays for transmission and power, and the power plant pays its gas supplier. If money stops anywhere in that chain, everything behind it stops too.
More power plants alone won't give us light
Politicians love to promise "more megawatts". But generating power is useless if you can't carry it to people.
Imagine a farmer who doubles his harvest, but the only road to the market is narrow and full of potholes, and the market stalls can only take so much. The extra yams rot on the farm. That is called stranded power. Power companies say they lost over ₦110 billion in the first half of 2026 to electricity that could not be delivered (Daily Trust).
TCN says the grid can now carry up to 8,700 MW (The Sun). The power companies say much less gets through in practice, and DisCos often refuse power because their own networks can't take it. Whoever is right on the day, one thing is clear: Nigeria needs at least 30,000 MW (allAfrica), and neither our grid nor our street-level networks are anywhere near ready to carry that.
So anyone promising to "generate more power" without explaining how it will be transmitted and distributed is only adding to the problem: more plants that sit idle, more debt for power we can't use.
Stop comparing us with Ghana and Niger
"Even Ghana has light!" We hear it all the time. But the comparison is unfair, because it ignores how many people each country has to serve.
In total, Nigeria has far more power capacity. We have about 13,600 MW installed; Ghana has about 5,800 MW (MyJoyOnline), less than half of ours. But Ghana has about 34 million people (World Bank), while we have over 240 million, about seven times as many. For every million people, Ghana has about 170 MW installed. Nigeria has about 57 MW.
Think of two families cooking. One has a small pot of soup for five people; the other has a pot twice as big, but for forty people. The bigger pot still leaves everyone hungry. That is Nigeria.
Niger is an even clearer case. A large part of its electricity is actually bought from Nigeria. When Nigeria cut its supply to Niger from 80 MW to 46 MW in 2025, Niger lost 30 to 50% of its available power and had to start blackouts (Legit.ng). Togo and Benin also import power from us (BusinessDay). Part of the "stable light" in our neighbours is Nigerian electricity.
This does not mean we are doing fine. It means the right question is not "why can't we be like Ghana?" but "how do we serve 240 million people?" That is a far bigger job, and it needs a far bigger plan.
What past governments tried
NEPA was formed in 1972. By 1999, fewer than 20 of Nigeria's 79 power plants were working (Daily Trust). Every government since has had a big plan:
- Obasanjo (1999–2007) launched the National Integrated Power Project in 2004: ten new gas power plants meant to add thousands of megawatts by 2008 (Springer). Many were finished years late, and some still struggle for gas today.
- Jonathan (2010–2015) sold the power plants and DisCos to private investors in 2013 for about $2.5 billion, keeping transmission (Daily Trust). Many buyers lacked money and expertise, borrowed in dollars at about ₦155 to the dollar, and were then forced to sell power below cost. At least six DisCos have since been taken over by banks or AMCON (allAfrica).
- Buhari (2015–2023) signed the Siemens deal, the Presidential Power Initiative, in 2019 to raise reliable supply to 7,000 MW by 2021 and 25,000 MW by 2025 (Daily Trust). By the time he left in 2023, even the first target had not been met.
The pattern is the same each time: a big promise, a short term in office, and a bill handed to the next government. DisCos still lose about ₦44 of every ₦100 worth of power they receive to theft, bad equipment and unpaid bills (BusinessDay).
The meter problem
Imagine a water vendor who guesses your bill because he has no way to measure what you fetched. You think he's cheating; he thinks you're stealing. Nobody pays properly. That is estimated billing.
By mid-2026, about 4.85 million of 12.6 million electricity customers still had no meter (Nairametrics). Without meters, nobody knows how much power was used or stolen, so the money chain leaks at the very first step.
Who really pays for your light
Since April 2024, customers have been grouped into bands by how many hours of light their area is promised: Band A at least 20 hours, B 16, C 12, D 8 and E 4 (Leadership). Band A pays close to the real cost. Everyone else pays far less, and the government promises to pay the rest to the power companies.
Here is what that looks like for a modest home using 150 units (kWh) a month, using the regulator's November 2024 figures for real cost and allowed price (allAfrica):
- Band A: you pay ₦31,400; real cost ₦34,800; government owes ₦3,300
- Band B: you pay ₦10,300; real cost ₦33,600; government owes ₦23,200
- Band C: you pay ₦8,500; real cost ₦31,400; government owes ₦22,900
- Band D: you pay ₦6,000; real cost ₦24,700; government owes ₦18,700
- Band E: you pay ₦5,900; real cost ₦21,800; government owes ₦15,800
For most homes, the government is promising to pay two to three times what the customer pays. Multiply that across millions of homes and it came to about ₦1.93 trillion in 2025 (BusinessDay).
The problem is the government mostly didn't pay. Of what it owed power companies for 2025, it paid only about ₦77 billion during the year (allAfrica). The unpaid promises piled up into a debt of over ₦6 trillion (BusinessDay).
Picture a mama put who sells food cheaply because a big man promised to pay part of every plate. He never pays. Soon she can't pay the rice seller, the rice seller stops supplying, and the street goes hungry.
That is why the current government's ₦4 trillion debt-clearing programme matters. By September 2026, it had raised over ₦1.12 trillion in bonds to pay what's owed (Leadership). No one will invest new money in a business that hasn't been paid for years.
But here is the hard part: you will not feel this money. Think of a man who earns ₦300,000 a month, but owes so much from years of borrowing that ₦200,000 goes straight to his creditors. His family sees no new furniture, no better food, no school upgrade, even though he is spending a lot. Paying old debts doesn't buy anything new; it only stops the shouting at the gate and lets him borrow again.
It is the same with power. The ₦4 trillion set aside for old debts will not add a single new megawatt or meter. Without that debt, the same money could have bought a meter for every unmetered home in Nigeria more than six times over, at today's price of about ₦130,000 per meter (Techeconomy). That is the true cost of years of unpaid promises.
Gas: the weakest link
About 70% of our grid power comes from gas (Legit.ng). For every ₦100 a gas plant earns, about ₦70 goes to its gas supplier. With power companies unpaid, gas suppliers are owed about ₦3.3 trillion and now demand cash before supplying (allAfrica). Add pipeline vandalism, and plants sit idle.
Nigeria has over 215 trillion cubic feet of gas reserves (Nairametrics). For years, the money that could have built gas pipelines went into keeping petrol cheap instead. It is like owning a farm full of food while your kitchen has no cooking gas.
There is real progress here, though it came late. The OB3 pipeline, started in 2012 to link the eastern gas fields to the west and north, was finally declared ready for first gas in 2026 (Zawya). The $2.8 billion AKK pipeline, which will carry gas from Ajaokuta through Abuja and Kaduna to Kano, has completed its main line, with the last stations still being finished (THISDAY). Together, they could finally bring gas to power plants and factories in the North. But a pipeline only helps when gas flows through it and the bills are paid.
What this government is doing, and where it falls short
To be fair, the Tinubu government has done more groundwork than most:
- It signed the Electricity Act 2023, letting states run their own power markets.
- It moved Band A customers to near-real prices, and launched the ₦4 trillion debt programme.
- It pushed the Siemens deal forward. Siemens has delivered 10 mobile substations and 10 large transformers, adding about 984 MW of transmission capacity, with two of five new substations due by December 2026 (Vanguard).
- Metering jumped from about 47% of customers in December 2024 to 57% a year later (Channels TV), and 63% by August 2026.
- The grid collapses less often: about 7 times a year on average under this government, compared with about 13 under Buhari (Intelpoint).
So why don't Nigerians feel it? Because fewer collapses is not the same as more power. Think of an old car that no longer breaks down on the expressway, but still runs on a quarter tank. You are happy it doesn't stop, but you still can't go far. The grid now holds together more often, but it is still carrying only about 4,000 to 5,000 MW, because plants lack gas and money. The lights don't go off nationwide as often, but your street still gets load-shedding.
And the government could have done better:
- Debt: It took until December 2025, two and a half years in, to issue the first debt bond. By September 2026, only about ₦1.12 trillion of the ₦4 trillion had been raised, while the government paid barely 4% of its 2025 subsidy bill (allAfrica). Old debt is being cleared with one hand while new debt piles up with the other.
- Meters: Progress is real, but about 4.7 million homes are still on estimated bills (Blueprint). Metering is the cheapest, fastest way to fix the money chain, and it deserved a far bigger, faster national push.
- Siemens: The deal is seven years old, and the timelines keep slipping. A project meant to deliver 25,000 MW by 2025 is now celebrating two substations by the end of 2026.
Why you can't see quick results
Electricity is not like a road you can watch being built. It needs huge money, years of building and rare technical skill, and most of the work, such as substations, pipelines and transformers, is invisible to the public.
Take the Zungeru hydropower plant: planned since 1982, started in 2013, due in 2018, finished only in 2023 at a cost of about $1.3 billion (Wikipedia). One plant, ten years, 700 MW. A government that wants credit within one four-year term will always be tempted to promise megawatts instead.
The government cannot fund it alone: in 2026 it expects to earn about ₦34 trillion but plans to spend over ₦58 trillion (21st Century Chronicle). Private investors could, but look at why they choose roads instead. The Lagos–Calabar Coastal Highway is financed under EPC+F, with lenders providing 70% (Tribune), because tolls give them a clear way to be repaid. In power, the price is fixed below cost, millions have no meters, the government owes trillions, and loans are in dollars while bills are paid in naira. Lending to a toll road is like lending to a shop where everyone pays at the door. Lending to the power sector is like lending to a shop where most customers buy on credit and the government fixes the price.
The way forward: let the states build, close to the people
The easiest path now is for states to get massively involved in building their own power, and for us to stop relying on one fragile national grid.
The Electricity Act 2023 makes this possible. States can now set up and regulate their own electricity markets, and at least 15 have already taken over from the federal regulator (NERC).
Think of it like water again. Instead of one giant pump in Abuja pushing water through long, leaky pipes to every town, each state builds its own boreholes close to where people live. Power generated near the people who use it does not need expensive long-distance transmission lines. States can build:
- Solar farms and mini-grids that can be installed in months, for towns, markets, schools and clinics.
- Small gas plants near industrial clusters, fed by dedicated gas.
- Hydro, where rivers allow. Nigeria uses only about 2 GW of an estimated 14 GW of hydro potential (Energy & Utilities).
- Coal, in states with deposits like the Benue–Kogi belt, where no coal plant runs today (Sweetcrude Reports), though it pollutes and is harder to finance.
States that can't afford it alone can pool resources with their neighbours through the regional development commissions, building shared plants and local grids for a whole zone.
But none of this escapes the basic rule: a state-owned plant still needs a meter on every house and customers who pay a fair price for what they use. Otherwise, states will simply copy Abuja's mistakes on a smaller scale.
So when governorship aspirants come asking for your vote, ask them:
- Has our state set up its own electricity regulator? If not, why not?
- How much new power will you build in our state, and where?
- How will you get meters into every home?
- Will our state subsidise tariffs, and how will you actually pay for it?
- Will you partner with neighbouring states to build shared power projects?
A bigger bet: batteries
There is a bigger opportunity hiding under our feet. Nigeria has lithium, the key ingredient in the batteries that power phones, electric cars and solar storage. For years, we dug it up and shipped it out raw, the same mistake we made with crude oil.
That is starting to change. In July 2026, a $250 million plant in Nasarawa began processing about 3 million tonnes of lithium ore a year (Semafor), and the government says raw mineral exports without local processing will no longer be allowed (Premium Times). But processing ore is only the first step. The real value lies in making battery materials, cells and full batteries here.
This is where Nigeria should place a huge, focused bet. Batteries solve two problems at once: they store solar power for the night, which makes state mini-grids reliable, and they put Nigeria inside one of the fastest-growing industries in the world. If we channel our limited power-sector resources into building that value chain, from mine to battery, within a few years Nigeria could be a serious player in green technology, selling finished products to the world instead of raw rocks.
Someone has to pay
Nigerians want constant light, low tariffs and no government debt, all at once. We cannot have all three. Electricity costs money to produce, and someone must pay: the customer, the taxpayer through a subsidy that is actually funded, or those who can afford more paying more so the poorest pay less.
We are already paying, through generators, fuel and fumes. But there is reason for hope. For the first time in years, the foundations are actually being laid: gas pipelines finished, new substations rising, old debts being paid down, meters going up, and states free to build their own power. Foundations are boring and invisible, but every house that stands rests on one.
It all comes back to a meter on every wall and a willingness to pay our fair share. If we hold our leaders, federal and state, to account and agree to pay the real price, Nigeria can have light within our lifetime. Until then, the darkness is the price.
Discussion · 07
Comments
Yusuf Hadi
This is a very insightful and well-explained analysis of Nigeria's electricity crisis. One important point I take from this article is that Nigeria's problem is not simply a lack of power generation capacity, but also weaknesses in transmission, distribution, gas supply, financial management and accountability. I particularly appreciate the emphasis on decentralising electricity generation and allowing states to develop solutions that address their local needs. However, beyond policies and promises, Nigerians need measurable results, transparency and sustainable implementation. We cannot continue to invest billions in the power sector without experiencing meaningful improvements in our daily lives. Nigeria has the resources and potential to achieve reliable electricity; what we urgently need is effective leadership, proper planning and consistent commitment.
▸1 replyHide replies
'Leye
Your comment only sufgest you either didnt read or you didnt understand the article, there is no way you read and understood and you will still come to a conclusion that effective leadership is the solution to this power problem. The best any president can do to overhaul Nigerians problems is putting policies in place to correct the years of economic decadence and then we pray for sustainability l, that is why a dull Obi should never rule Nigeria after Tinubu because he will tske us backward, we need someone who will sustain Tinubu's policies until we get to the promise land. If you read the article you will see where the author stated what the government is doing, why it looks like we are not feeling the impact and the policies they have put in place to bring change
Alex Balogun
This is such a brilliant piece. How does transmission limits affects new generating capacities that coild be built by states though? It would be also be a great addition is anyone is documenting any successful models from states. Well done, well written.
Ibrahim
Thanks for your analysis. We need a strong will power to improve power generation and transmission. Nigerians need to do better in any capacity we find ourselves.
Oluwabusayo Ajayi
This is incredible. I picked the lithium minerals one can actually work on
George
This is a great piece. The simple solution is to commit funds to beef up the grid and make the cost of power generation lower. Why should we be flaring gas that could be used to reduce the cost of power generation?